Adcock recently completed a major project at St Andrew’s Healthcare site at Birmingham, which consisted of replacing 28 Mitsubishi Electric VRF condensing units and all main pipework to internal BC boxes supplying the systems in all 5 buildings . This project was completed over 14 weeks and included 4 crane lifts to place external units into position. All work was coordinated with minimal disruption to service users and staff. Adcock has decades of experience carrying out works at similar healthcare sites where continuous operation is crucial during install works.
As a Diamond Quality Partner with Mitsubishi Electric, Adcock was able to offer the client a wealth of experience with this type of installation and the added benefit of a seven-year warranty.